Starting at 6 am, January 15, 2024, the southbound Hall Boulevard on-ramp will close for two months.
New local road impacts:
- Nighttime single lane closure on North Hall Boulevard on Jan. 10 and Jan. 11.
- One of the two westbound lanes on Hall Boulevard between Scholls Ferry Road and Cascade Avenue will close in mid-January for several months.
Ongoing construction impacts:
- Ramp impacts
- The right turn lane on the southbound OR 99W off-ramp is closed for several months. Drivers can still make a right turn from the off-ramp by using the adjacent lane.
Overpass impacts:
- One of the two westbound lanes on the Allen Boulevard overpass is closed for several months for bridge rail improvements. The lane is expected to open in 2024.
- One of the two westbound lanes on the Denney Road overpass is closed for several months for sidewalk and bridge rail improvements. The lane is expected to open in 2024.
- One of the two westbound lanes on the Hall Boulevard overpass (between Scholls Ferry Road to Cascade Avenue) has been closed again to safely accommodate bridge widening work. The closed lane will provide crews with the space they need to finish widening the overpass. More information is available on our Bicycle and Pedestrian Improvements page.
Pedestrian impacts in several places:
- The sidewalk on the north side of the Denney Road overpass. Temporary pedestrian detours are in place on the overpass.
- The sidewalk on the north side of Hall Boulevard near Cascade Avenue. A temporary pedestrian detour is in place on the south side of Hall Boulevard.
- The sidewalk on the north side of OR 99W by the southbound OR 217 off-ramp. A temporary pedestrian detour is in place.
General impacts:
- Intermittent closures of existing auxiliary lanes and shoulders on OR 217 and nearby local roads throughout the project area. Various on- and off-ramps are narrower, but will remain open, unless stated otherwise.
- Intermittent nighttime work throughout the project area. We have a 24/7 noise hotline for night noise concerns: (503) 412-2349.
- Crews are transporting dirt and materials from the project area to a site on ODOT property at the I-5 and I-205 interchange. Crews are also staging dirt and materials near SW Denney Road and SW 105th Avenue. Some materials are delivered at night and nearby neighbors may hear some noise.